How fast Can an Expert Develop a Self Storage facility from scratch?
- May 4
- 1 min read
Updated: 6 days ago

Much faster than the average of 3 – 4 years.
Description Time
Find Land 2 months
+ Build team
+ Prepare design standards
Close on land 1 month
+ prepare Concept Plan
+ Start boundary survey
+ Get proposal for Engineering
+ Get Proposal for Architectural design
Design site plan and building plans 2 months
Site plan approvals & related approvals 2 months
+ Discussions with Bank 2 months
+ Discussions with Bidders
Building permit plan approval 1 month
+ construction bid 1 month
+ Initial bank application
Bank Approval 1 Month
Construction 11 months
Contingency time 1 Month
Start to Grand opening = 24 months
Now remember I said time for a self storage expert. Most people are not experts and will take longer.
Even if you double the time and then add in a couple more years to fill your facility, there is no better way to build long-term income and wealth.
In the end, the biggest amount of money and time lost or saved is during Construction. If you want to save both time and money during construction, you are invited to our
FREE WEBINAR Thursday, May 15, 2026, 11 AM
Build Smarter
Avoid the Pitfalls of Self Storage Construction
Register Now
• The costly missteps no one warns you about
• How to navigate construction “landmines” with confidence
• Tips to lower costs without cutting corners
• Expert insights from experienced storage builders





Comments